  Construction Sequence >
Construction
 
Construction
 
  Construction : Level 1 Start
Week
Finish
Week
Total
Weeks
 
  Borewell 12 12 1  
  Excavation as per drawing 13 15 3  
  Footing/Foundations* 16 17 2  
  Pillars/Columns (Up to plinth level) 18 19 2  
  Soil filling in trenches and
compaction till ground level
19 19 1  
  Plinth Construction* 20 21 2  
  Pillars up to lintel level* 22 23 2  
  Lintel* 24 27 4  
  Pillars up to roof level* 26 27 2  
  Soil filling and compaction till
plinth level
26 27 2  
  Roof Slab* 28 32 5  
           
  Construction : Level 1 Start
Week
Finish
Week
Total
Weeks
 
  Brick Work & Curing 28 34 7  
  Ducts for electrical wiring 35 36 2  
  Frames for doors & windows 35 35 1  
  Plastering & Curing 37 39 3  
  Water Treatment, Heat Treatment 40 40 1  
           
  *Including reinforcement, shuttering, concreting, curing, deshuttering  
 
 
 
   
  Too many doubts in your mind? Looking for the right advice?
Click Here
to send in your queries.
 
     
   
  If you want to meet us for a discussion, please visit any of our Help Centres.
Click here to find a Help Centre near you.
 
       
  © 2006 ACC Limited
Disclaimer | Contact Us | Site Map