| |
FAQs >
Brickwork |
|
 |
| |
Q.
How to test the quality of Bricks at small construction sites?
Normally the bricks are tested for Compressive strength,
water absorption, dimensional tolerances and efflorescence.
However at small construction sites the quality of bricks can be
assessed based on following, which is prevalent in many sites. |
- Visual check - Bricks should be well burnt and of
uniform size and color.
- Striking pf two bricks together should produce a
metallic ringing sound.
- It should have surface so hard that can’t be scratched
by the fingernails.
- A good brick should not break if dropped in standing
position from one metre above ground level.
- A good brick shouldn’t absorb moisture of more than
15-20% by weight, when soaked in water For example, a good
brick of 2 kg shouldn’t weigh more than 2.3 to 2.4 kg if
immersed in water for 24 hours.
|
Q.
What is the importance of Frog (depression in the brick) in
masonry?
The depression in the brick on top (approximately 100mmX40mm
X10 to 15mm deep) is called the frog and the mortar is filled in
the frog while laying the bricks in masonry work to help in
bonding and acting as a shear key against horizontal loads. |
| |
Q.
What precautions to be taken in brick masonry work?
- Bricks should be soaked in water for adequate period so
that the water penetrates to its full thickness. Normally 6
to 8 hours of wetting is sufficient.
- A systematic bond must be maintained throughout the
brickwork. Vertical joints shouldn’t be continuous but
staggered.
- The joint thickness shouldn’t exceed 1 cm. It should be
thoroughly filled with the cement mortar 1:4 to 1:6 (Cement:
Sand by volume)
- All bricks should be placed on their bed with frogs on
top (depression on top of the brick for providing bond with
mortar).
- Thread, plumb bob and spirit level should be used for
alignment, verticality and horizontality of construction.
- Joints should be raked and properly finished with trowel
or float, to provide good bond.
- A maximum of one metre wall height should be constructed
in a day.
- Brickwork should be properly cured for at least 10 days.
|
| |
Q.
How many days of curing are adequate for Brickwork?
The brickwork should be cured with water and kept moist for
minimum 7 to 10 days period for proper development of strength. |
| |
Q.
What is the difference between a load bearing masonry structure
and RCC framed building?
Load-bearing masonry structure transfers the structural load
of the building through the masonry walls and masonry footing
and do not have concrete columns and footing. A RCC framed
building would have columns (pillars) arising out of
foundations, which bear the load of the building through
column-beam frame and transfer the load to foundation. Load
bearing walls are not economical in most cases if the building
has more than three stories. RCC framed system is slender and
having flexibility of shifting it’s internal light weight
partition walls. |
|
|
|
|
Back to Questions |
| |
|
|
|
| |
 |
|
 |
| |
 |
Too many doubts in your mind? Looking for the right advice?
Click Here to send in your queries. |
|
| |
|
|
| |
 |
|
 |
| |
 |
If you want to meet us for a discussion, please visit any of our Help Centres.
Click here to find a Help Centre near you. |
|
| |
|
|
|
| |
© 2006 ACC Limited
Disclaimer |
Contact Us |
Site Map |
|
| |
|
|
|